Aberdeen junction works blown behind schedule

06/01/2022 | CHRIS AMES

The expected completion of the Scottish Government’s £18m A92/A96 Haudagain Improvement has been put back to the spring.

The Haudagain Roundabout is a major road junction in Aberdeen. In 2019 Farrans, a sister company of Tarmac and part of CRH was awarded a £17.6m design and build contract by Transport Scotland to reconfigure the junction.

An earlier view of the project, which is now 'well advanced'

Minister for transport Graeme Dey said the project is ‘well advanced and remains within budget’.

However, Transport Scotland said pandemic impacts, supply chain issues and recent storms had combined to push back timescales, with the project now opening to traffic by the end of March 2022.

The pandemic continued to disrupt progress this year with key work having to be rescheduled due to the impact on workforces.

Transport Scotland added that industry-wide supply chain issues affected the availability of materials hitting timescales despite the contractor taking mitigation measures by re-sequencing work and sourcing from alternative suppliers.

A large proportion of the remaining work, including road surfacing, could not be carried out during recent adverse weather including storm Arwen and Barra.

Mr Dey added: ‘The contractor has reported impacts to programme critical work within the previous month due to adverse weather from Storm Arwen and Storm Barra. Until these recent events, our contractor had been able to maintain an anticipated completion date within the Winter 2021 period, despite the challenges posed throughout 2021 by the ongoing COVID-19 pandemic and industry-wide supply chain issues.

‘We have consistently highlighted the potential risk such events could have in causing a delay to the expected completion date for this project. Likewise this revised date remains subject to no further disruption from events such as adverse weather or impacts from the ongoing pandemic.’

Highways InProfile

latest magazine issue
Highways jobs

Chartered Civil Engineer – Highways Specialist

£65,000 - £80,000 based on experience.
We are looking for a driven and experienced Chartered Civil Engineer with a strong background in highways engineering to join our team. Bristol based offices. Hybrid (2 days in office) or remote working for the right candidate.
Recruiter: W.D.M. Limited

Professional Services Partnering Manager

Grade 13 £49,178 - £52,937 per annum
Are you passionate about infrastructure, partnership management and making a real impact? Derbyshire
Recruiter: Derbyshire County Council

Highways Technical Assistant

£29,064 - £31,537 per annum
Would you like to be part of one of our friendly, welcoming Highways teams, who are proud to manage all aspects of the highway network? Kirby Misperton, Malton
Recruiter: North Yorkshire Council

Highways Technical Assistant

£29,064 - £31,537 per annum
Would you like to be part of one of our friendly, welcoming Highways teams, who are proud to manage all aspects of the highway network? Boroughbridge, York
Recruiter: North Yorkshire Council

Highways Technical Assistant

£29,064 - £31,537 per annum
Would you like to be part of one of our friendly, welcoming Highways teams, who are proud to manage all aspects of the highway network? Whitby, North Yorkshire
Recruiter: North Yorkshire Council

Highways Technical Assistant

£29,064 - £31,537 per annum
Would you like to be part of one of our friendly, welcoming Highways teams, who are proud to manage all aspects of the highway network? Selby, North Yorkshire
Recruiter: North Yorkshire Council

Highways Technical Assistant

£29,064 - £31,537 per annum
Would you like to be part of one of our friendly, welcoming Highways teams, who are proud to manage all aspects of the highway network? Skipton, North Yorkshire
Recruiter: North Yorkshire Council

Senior Highways Engineer

£52,194 - £55,323 per annum
We’d love you to join us at the London Borough of Hounslow! Hounslow (City/Town), London (Greater) (GB)
Recruiter: Hounslow London Borough Council

Highways Technical Assistant

£29,064 - £31,537 per annum
Would you like to be part of one of our friendly, welcoming Highways teams, who are proud to manage all aspects of the highway network? Thirsk, North Yorkshire
Recruiter: North Yorkshire Council

Roads Strategy Director & National Highways Client Director

circa £100,000
Transport is fundamental to everyday life, connecting people to work, education, leisure and opportunity. Leeds / Birmingham / London
Recruiter: Department for Transport

Bridges Engineer

Grade 8 - Grade 10
The Key purpose of this position within the Highways Network Management Team Wakefield, West Yorkshire
Recruiter: Wakefield Council

Assistant Highways Network Technician - WMF2343e

£26,403 - £26,824
This role will be part of the Network Team in the South Lakeland area based in Kendal. Kendal, Cumbria
Recruiter: Westmorland and Furness Council

Principal Engineer - Adoptions

£46,878 - £50,071
We are seeking an experienced and motivated Principal Highways Engineer to join our Highways Development Management team. Northamptonshire
Recruiter: West Northamptonshire Council

Asset Senior Maintenance Engineer (CDC)

Grade 10, £47,154 – £51,235
Do you have a positive approach to work and enjoy the challenge of a busy role? Doncaster, South Yorkshire
Recruiter: City Of Doncaster Council

Arboricultural Consultant

£36168.0000 - £42551.0000 per annum
Arboricultural ConsultantPermanentFull Time, 37 hours per week£36,168 to £42,551 per annumLocation
Recruiter: Essex County Council

Senior Engineer

Starting Salary from £43,545 based on skills and
Job TitleSenior Engineer (x2 v... Frogmore Complex, Wandsworth, London,
Recruiter: London Borough of Richmond upon Thames and London Borough of Wandsworth

Assistant Traffic Management Technician - WMF2311e

£26,403 - £26,824
This is a predominantly office-based role with some site visits required. Penrith, Cumbria
Recruiter: Westmorland and Furness Council

Senior Lawyer Planning and Highways - WMF2312e

£56,883 - £59,198
To be a success in our Legal Team you will have experience as a Planning and Highways Lawyer Cumbria / Various
Recruiter: Westmorland and Furness Council

Civil Engineering Technician (HDM)

Grade 4 - Grade 6
Do you want to join a team helping to shape the future of Wakefield through Highways Development Management? Wakefield, West Yorkshire
Recruiter: Wakefield Council

Highways Maintenance Operative Apprentice

£28,729.00 per annum (Subject to review)
As part of your apprenticeship, you will be enrolled onto a Lead Traffic Management operative course Staffordshire
Recruiter: Amey
SUBSCRIBE NOW

Latest Video

Subscribe to Highways today to ensure you keep your finger on the pulse of everything happening in the UK road network throughout the year.

SUBSCRIBE NOW